The extensive reinforcement works in various areas continued. In Experimental Hall 1 (D02) rebar was put down both for the Monolith vault and the second part of the Active Cell base slab. The remaining E-area lab buildings, E03 and E05 , were reinforced in preparation for bottom slab castings this week. The reinforcement works also continued in the Sprinkler Building (H10) , first casting pending. In the Accelerator tunnel (G01) injections continue to be followed by the final touch-up painting. In the Central Utility Building (H01) the installation of facades on roof level is on-going. The installation of link plates connecting the roof of the Gallery Building (G02) with the slope on top of G01 progressed well and have now reached all the way to section 6 of the Gallery building.