Target
In 'Accelerator to Target' (A2T), work on lift shafts, the installation of steel plates for shielding purposes ,and partition walls is ongoing. Construction of high pillars continues on both sides, and in early May reinforcements and water stops for the facade walls will commence, with the first casting planned for 13 May.
The last casting (4 out of 4) for the Monolith high bay slab is planned for 2 May , when we will also cast the edge beam. In May we will commence construction of two houses on top of the slab, which will be placed on the east side of the vault.
In the Utility and Active Cell, internal structures and construction of walls on level 3 are ongoing, as well as reinforcement of the High Bay slab. First castings are scheduled for 9th May (Utility) and 14th May (Active Cell).
Both D06 (substation building) and the Admin part of D02 are ready for superstructure works. Skanska Sub-Contractor, Severfield, is projected to start with prefab erection next week, initially in D06.
Experimental Halls
E01 (Experimental Hall 3) is on time for handover to ESS in August. Some final touches, including the installation of a crane hook for the overhead crane and lightning protection for the building, remain. At the same time we are in progress with pre-inspections and testing prior to a Sectional Handover Inspection in mid-May. Remaining issues shall then be solved before the Sectional Handover Meeting planned for 15 August.
The status of Experimental Hall 1 (D01) and Experimental Hall 2 (D03) is as follows:
D01 - 60 bottom slabs cast, 18 to go (78% complete)
D03 - 30 bottom slab cast, 17 to go (64% complete).
Grinding of the floors is completed in the large E01 hall and E02 Beamline Gallery, and a dust binder has been applied. Interior works continue in lab buildings E03 and E04. Details, such as door posts, glazed wall sections for the offices, toilets, tiling, radiators, kitchen fittings, various installations and cabling, are all in progress.
Accelerator
Stub installations are ongoing in the Accelerator tunnel, with more than 500 waveguide units installed (10%+ complete) so far. Beam commissioning activities are currently ongoing for the Ion Source and LEBT.
In the Klystron Gallery, steel structure erection is continuing, as well as rack installations along the stubs and walls. Waveguide components are being installed throughout the Gallery, and in Test Stand 2 preparations are ongoing to move the Medium beta cryomodule inside the test bunker.