Skip to main content

Main navigation

  • About ESS
    • The ESS Mandate
      • The ESS Story
      • Neutrons: The Science of Everyday Life
    • ESS Organisation
      • Governance
      • Committees
    • News & Press
      • Media Bank
      • Web Articles
    • Publications
    • Legal
      • ESS Privacy and Cookies Policies
    • Contact ESS
      • Tours & Visits
      • How to Find Us
      • Interactive Map
  • Science & Instruments
    • Science Using Neutrons
      • Chemistry of Materials, Magnetic & Electronic Phenomena
      • Engineering Materials, Geosciences, Archeology & Heritage Conservation and Fast Neutron Applications
      • Life Science & Soft Condensed Matter
      • Particle Physics
    • Instruments
    • Instrument Technologies
      • Chopper Systems
        • Choppers Research & Development
      • Detector Systems
        • Detectors Research & Development
      • Motion Control & Automation
      • Neutron Optics & Shielding
    • Data Management & Software Centre
      • Computing Centre
    • Science Support Systems
      • PREMP
      • FLUCO
      • TEFI
      • DEMAX
      • SULF
      • MESI
      • SCUO
    • Workshops & Facilities
  • Technology
    • Accelerator
      • How It Works
      • LINAC
      • Beam Physics & Beam Diagnostics
      • Cryogenics
      • Vacuum
      • Radio Frequency Systems
      • Accelerator Test Stands
    • Target
      • How the Target works
    • Controls
  • Building ESS
    • Partnerships & Collaborations
    • The Building Project
      • Site, Architecture & Sustainability
      • Licensing & Planning
      • Radiation Protection & Safety
    • Progress reports from the ESS site
    • Aerial Views
  • Partners & Industry
    • In-Kind Contributions
    • Procurement
      • Procurement Listings
      • Contract Award Notices
    • Industrial Suppliers
    • Grants & Events
      • Grants
      • Events
  • Careers
    • Vacancies
    • Living & Working in Scandinavia
      • In Sweden
      • In Denmark
    • ESS Family Support
Webmail
ESS Inside
  • About ESS
    The ESS Mandate ESS Organisation News & Press Publications Legal Contact ESS
  • Science & Instruments
    Science Using Neutrons Instruments Instrument Technologies Data Management & Software Centre Science Support Systems Workshops & Facilities
  • Technology
    Accelerator Target Controls
  • Building ESS
    Partnerships & Collaborations The Building Project Progress reports from the ESS site Aerial Views
  • Partners & Industry
    In-Kind Contributions Procurement Industrial Suppliers Grants & Events
  • Careers
    Vacancies Living & Working in Scandinavia ESS Family Support

Secondary navigation

  • Contact
  • Press
  • Privacy
  • Behind ESS
Home

Main navigation

  • About ESS
    ess long pulse slide
    The ESS Mandate
    organisation
    ESS Organisation
    News and Press
    News & Press
    alt
    Publications
    legal and ip
    Legal
    contact ess
    Contact ESS
  • Science & Instruments
    Science using neutrons
    Science Using Neutrons
    instruments
    Instruments
    detector aquarium ess
    Instrument Technologies
    dmsc
    Data Management & Software Centre
    sss magnet
    Science Support Systems
    linkoping detector coatings workshop ess
    Workshops & Facilities
  • Technology
    ess accelerator
    Accelerator
    target monolith
    Target
    ess ics
    Controls
  • Building ESS
    Partners & Collaborations
    Partnerships & Collaborations
    Building project
    The Building Project
    weekly construction updates
    Progress reports from the ESS site
    ess aerial snow
    Aerial Views
  • Partners & Industry
    tartu pump probe
    In-Kind Contributions
    procurement
    Procurement
    ess target twister shaft
    Industrial Suppliers
    partner day
    Grants & Events
  • Careers
    careers
    Vacancies
    scandinavia
    Living & Working in Scandinavia
    family
    ESS Family Support

25 April 2022

Target Monolith

The installation of outer shielding blocks is complete. Three layers of shielding, weighting approximately 1500 tonnes, are in place surrounding the Monolith vessel. Survey and alignment of the area is now in progress.

In preparation for a cleanroom installation, which will be built around the Monolith connection cell, the entire high bay is subject to deep cleaning.

Active Cell

The in-cell grapple crane for the Active Cell is place. The crane beam, crab hook and wheel boxes were preassembled on the high bay, before the lift was conducted. In-kind partner UKAEA are responsible for the installations of a remote handling system in the Active Cell.

Target mock-up and test stand

The Mock Up and Test Stand (MUTS) has been cleaned and covered with protection. In here, the Target wheel, drive unit and shaft will be tested soon.

In-bunker installations

Bunker wall blocks have been temporarily removed in the south sector (for instruments ODIN and DREAM) as well as the west sector (for NMX, CSPEC and BIFROST). Whilst preparations to install the wall inserts are ongoing in the two short instrument halls, the wall inserts are assembled, aligned and vacuum tested inside a tent in the long instrument hall.

The first in-bunker installation will take place on the west side, where the wall insert and neutron guide for BIFROST will be lifted in place.

Normal Conducting Linac

Whilst the Accelerator operations team continues conditioning of the Drift Tube Linac (DTL) and beam commissioning activities from the control room, fitting of equipment to allow for 12 operator work stations in the ESS main control room goes on.

Preparations for a Safety Readiness Review allowing for beam commissioning up to the faraday cup of DTL tank 1 are ongoing. The review is to be held on 4-5 May.

Siteplan Archive
D02 AC grapple crane

A grapple crane, to move items between the two cells of the Active Cell, is lifted in place.

D02 TH MUTS

Target Mock-up and Test Stand getting ready for tests of the Target wheel handling to be performed.

D02 Monolith SAM

Survey and alignment activities are ongoing in the Monolith area.

D02 Monolith

Monolith outer shielding installation completed.

D03 west bunker wall open

Preparations for in-bunker installations in Experimental Hall 2, west sector.

D01 south bunker wall open

Preparations for in-bunker installations in Experimental Hall 1, south sector.

Bunker wall inserts BIFROST and ODIN

Bunker wall inserts for ODIN and BIFROST under preparation.

D02 Target high bay

The Target high bay is getting a spring clean.

ESS Main Control Room

More screens are to be installed in the main control room, located on the first floor of the Target Entrance building.

G-buildings under sombrero

DTL conditioning as well as beam commissioning is in progress in the first part of the Accelerator tunnel.