This week at the construction site, casting is ongoing at the Target Building Utility area.
The next level wall of the Active Cells area is ready for heavy concrete. In the A2T (Accelerator to Target) area, 12 pillars as well as the first tunnel wall on the south side will be cast.
The ESS Logistics Building (F03) is approaching a weathertight building with sandwich panels in place and roof works in the final stages. The final levelling for the indoor slabs will start this week with concrete works to commence shortly.