The reinforced earthen slope between the Accelerator tunnel (G01) and the Gallery Building (G02) was completed and now awaits a link plate to connect the slope to the roof of the Gallery Building. The topfill for the Accelerator tunnel has now reached 65,500 cubic metres of clay, the equivalent of dumping 26 Olympic-sized swimming pools of earth over the area. Base slab castings are on hold due to the heavy snowfall, but wall casting in the Monolith area (D02) has continued on schedule. All fixed overhead cranes have now passed a third-party inspection. Interior, MEP and finishing work is ongoing in various parts of the Gallery and Cryo-Compressor (G04) buildings. And the first facility-based office, the Cryo Office, is being wired and plumbed for occupancy.