Casting of the 8,000 square metre Beamline Gallery (E02) base slab was completed, with the expectation that building construction will begin at the end of the summer. Powerheat’s installation of piping in the Cryo-Compressor Building (G04) is in full swing, while the recently installed pipes in the Gallery Building (G02) Cold Box are undergoing X-ray controls. Polyurethane injection continues in the Accelerator tunnel (G01) . The construction of the Monolith vault continues, and grouting of structures within the puck is being done. Ground preparations for the Sprinkler Building (H10) are nearing completion.